Quaker State

Whithin two years, Mainstream Construction Group provided this corporate client with construction services for four new units in Lakeland, Clearwater and Tampa Florida, Specializing in prototypical design, and utilizing its vast expertise to build hundreds of auto parts and repair stores, mainstream was able to construct each store in 60 days or less. The scope services included the excavation, waterproofing and poured-in-place concrete installation for the pit area prior to the erection of the concrete block facility.

No. Units Completed: 4 Units

Construction Time: 60 Days

Completed: 1996 - 1997

Combined Cost: $480,000 Combined